Repair & Maintenance
National Police Agency main building and annex reinforcement work
Address
Construction Year 2003.
Net Floor Area
Story
Building Type Public & Office Buildings
Structural System
  The main building reinforcement work was carried out from 7 p.m. to 6 a.m., and the existing beams, which lacked strength in the ceiling, were reinforced with the wire tension method without removing the entire ceiling or facilities of the floor.
The lower part of the water tank of the annex was designed as H-Beam reinforcement, but the air conditioning equipment was so complex that after 3D investigation, it was redesigned as a special reinforcement method rather than H-Beam reinforcement and the reinforcement work was completed.